Type-Tested Switchboards and Licensed Panel Builders in the UAE and Saudi Arabia
What replaced the type-tested label, how duties split between the original manufacturer and the panel builder, which reports and certificates to ask for, and how to run a factory acceptance test.
Switchgear companies in the UAE fall into three groups: global manufacturers with local offices, panel builders authorised to assemble a manufacturer's switchboard system, and independent builders with their own designs. The label matters less than the evidence. Ask any of them for IEC 61439 design verification reports for the system offered, routine test records for your panel and proof of partner status where claimed, then shortlist from switchgear and panel suppliers in the UAE.
This guide is for consultants, MEP contractors and procurement teams who must approve a panel builder or compare switchboard bids. It explains what replaced the old "type-tested" label, how responsibility is split between the original manufacturer and the panel builder, which certificates to ask for, and how to run a factory acceptance test. Which brands are specified, and the UAE and Saudi conformity rules, are covered in our guide to switchgear and panel brands in the UAE and Saudi Arabia. For the Kingdom, see switchgear and panel suppliers in Saudi Arabia.
From "type-tested" to "design verified"
Many Gulf tenders still ask for a "type-tested assembly". The phrase comes from IEC 60439-1, titled "Type-tested and partially type-tested assemblies", whose scope covered type-tested assemblies (TTA) and partially type-tested assemblies (PTTA). IEC lists that standard as replaced by IEC 61439-1:2009, with a withdrawal date of January 2009.
The IEC 61439 series dropped the TTA and PTTA categories. In their place it asks for design verification of the design and routine verification of every assembly built. The current editions are IEC 61439-1:2020 (general rules) and IEC 61439-2:2020 (power switchgear and controlgear assemblies). Part 1 states that it cannot be used alone: an assembly must comply with the relevant part, Part 2 onwards, read with Part 1.
The 2020 edition of Part 1 made four significant changes, according to its foreword:
power electronic converters, switch mode power supplies, UPS and drive systems are tested to their own product standards, but their incorporation into an assembly follows the IEC 61439 series;
a group rated current for circuits within a loaded assembly, with temperature-rise verification refocused on it;
requirements for DC;
class I and class II assemblies for protection against electric shock.
So when a specification says "type-tested", the practical translation is: design verified to IEC 61439-1 and -2 (2020) for the ratings and configuration offered, with routine verification of the actual panel.
IEC 61439-1 states that it applies whether an assembly is designed, manufactured and verified as a one-off or fully standardised and made in quantity, and that manufacture or assembly may be carried out by someone other than the original manufacturer. That is the basis of the panel-building model used across the Gulf. In practice the duties split like this:
Role
Who it usually is
Responsible for
Evidence to ask for
Original manufacturer
The company that designed the switchboard system: a global brand, or an independent builder with its own system
Design verification of the system (clause 10)
Design verification reports covering your ratings, form and configuration
Assembly manufacturer
The panel builder that builds your panel, either on its own design or on a brand's system
Building to the verified design and routine verification of each panel (clause 11)
Routine test certificate, drawings, proof that it builds the system as designed
The risk sits in the gap between the two. If a builder puts a brand's breakers into its own enclosure and busbar system, the breaker maker's certificates cover the breakers, not the assembly, so ask who verified the assembly design and for which ratings. A builder that uses a brand's complete switchboard system can point to the brand's verification, but only for configurations within the limits of that system.
What design verification covers
Clause 10 of IEC 61439-1:2020 lists the characteristics that must be verified for a design. The contents of the standard set them out:
Clause
Characteristic verified
10.2
Strength of materials and parts: corrosion, insulating materials, UV resistance, lifting, mechanical impact (IK code), marking, mechanical operation
10.3
Degree of protection (IP code)
10.4
Clearances and creepage distances
10.5
Protection against electric shock and integrity of protective circuits, including short-circuit strength of the protective circuit
10.6 to 10.8
Incorporation of switching devices and components, internal circuits and connections, terminals for external conductors
10.9
Dielectric properties: power-frequency and impulse withstand voltage
10.10
Temperature rise: by testing, by derivation of ratings for similar variants, or by verification assessment
10.11
Short-circuit withstand strength: by comparison with a reference design (checklist or calculation), or by test
10.12
Electromagnetic compatibility
IEC 61439-2:2020 added to this. Its third edition, published in July 2020, clarified the forms of internal separation (for forms above 1, live parts left energised in a switched-off functional unit need at least IPXXB protection) and added temperature-rise verification for naturally cooled assemblies with circuits above 1,600 A, using comparison with a reference design combined with calculation, and for actively cooled assemblies up to 1,600 A.
Two of these characteristics decide most disputes. Temperature rise sets the current the busbars and circuits can really carry, and the standard includes a clause on adjusting rated currents for alternative ambient temperatures, which matters at Gulf temperatures. Short-circuit withstand sets the fault level the panel survives; the standard allows comparison with a tested reference design, so ask which reference design and which test it relies on.
Routine verification: done on every panel
Clause 11 lists the routine checks that the assembly manufacturer performs on each panel before dispatch:
degree of protection against contact with hazardous live parts and ingress (11.2);
clearances and creepage distances (11.3);
protection against electric shock and integrity of protective circuits (11.4);
incorporation of built-in components (11.5);
internal electrical circuits and connections (11.6);
terminals for external conductors (11.7);
mechanical operation (11.8);
dielectric properties (11.9);
wiring, operational performance and function (11.10).
The routine test certificate should list each item, the result, the test equipment used and the panel's serial number. A certificate that only says "tested OK" is not enough.
OEM partner programmes
Several brands run formal programmes for panel builders who build on their systems. Two examples from the makers' own pages:
Siemens says certified SIVACON technology partners manufacture SIVACON S8 cubicles regionally, and provides a partner finder on its site. SIVACON S8 is developed and tested to IEC 61439-2.
Schneider Electric lists a "Panel Building Systems" category on its UAE site, with the PrismaSeT family from PrismaSeT G (up to 630 A) to PrismaSeT 6300, including PrismaSeT HD for harsh environments and PrismaSeT I for applications including PCC and MCC up to 3,200 A.
Other brands have their own partner arrangements; ask the bidder for them in writing. In every case, check that the partner status is current, that it covers the specific system offered, and whether the brand inspects or audits the builder's work.
When you evaluate a panel builder, ask for these with the bid, not after award:
Design verification reports for the system, covering your rated current at your ambient, short-circuit rating and duration, form of separation and IP rating. Check that the configuration tested is the one offered.
Partner or licence letter from the brand, if the bid relies on a brand's system, naming the builder and the system.
Arc-fault test evidence, if specified, and the document it was tested to; our guide to motor control centres explains the IEC TS 61641:2026 approaches.
Component certificates for breakers and devices, including country conformity (ECAS or G-Mark in the UAE, SABER in Saudi Arabia).
Quality system and factory details: workshop location, test bay, test equipment calibration.
Sample routine test certificate from a previous panel, so you can see what you will receive.
Agreed items list. Annex C of IEC 61439-1 summarises the requirements that are subject to agreement between the assembly manufacturer and the user. Use it to confirm that ambient, form, IP, cable entry and the rest are written into the order.
Factory acceptance test
A factory acceptance test (FAT) is where the buyer or consultant witnesses the routine verification and checks the panel against the drawings. A useful FAT plan covers:
a visual and dimensional check against approved drawings, nameplates and labels;
a check that devices, busbar sizes and torque markings match the design;
the dielectric test and protective circuit continuity;
functional tests of controls, interlocks, transfer schemes and metering;
racking of withdrawable units and operation of every handle;
review of the completed routine test certificate before shipping.
Agree the FAT procedure at the drawing approval stage, including how failures are recorded and retested. For MCCs, add the starter and communication tests listed in our MCC guide.
UAE and Saudi approvals
UAE
Beyond product conformity, which our guide to ECAS and EQM conformity explains, consultants and utilities may keep their own approved lists for switchgear makes and panel builders. Ask the consultant which list applies and what a builder must submit to join it, and confirm whether the utility needs to inspect panels that connect to its network.
Saudi Arabia
Imported components and assemblies go through SABER under SASO technical regulations; see our guide to SASO and SABER certificates. Large clients and utilities may prequalify panel builders and keep approved manufacturer lists; check yours before bids are invited. LV switchgear and distribution board suppliers can usually tell you which lists they are on.
Brands with panel-builder systems
Siemens builds its SIVACON S8 network through certified technology partners. Schneider Electric offers the PrismaSeT panel building systems and larger Okken and BlokSeT switchboards; Saudi buyers can see Schneider Electric in Saudi Arabia. For ABB, Eaton, Hager, Legrand, Socomec and other makers, see the main guide, and ask each bidder for the partner documents above. The breakers inside the panel are explained in our guide to circuit breaker types.
Panel builder shortlist checklist
Is the bidder the original manufacturer of the design, or building on a brand's system?
Do the design verification reports cover the rated current, short-circuit rating, form and IP offered?
Are ratings given at your design ambient, with the derating method stated?
Is partner status current, in writing and for this system?
Is there a test bay with calibrated equipment for dielectric and functional tests?
Will the routine test certificate list every clause 11 item with results and serial number?
Is the builder on the consultant's, utility's or client's approved list?
Are component conformity certificates available for the country?
Is the FAT procedure agreed, with witness points?
To get several qualified builders to quote at once, post a requirement on ListGCC with your single-line diagram and specification.
The term comes from IEC 60439-1, which covered type-tested and partially type-tested assemblies. IEC lists that standard as replaced by IEC 61439-1 in 2009. Today the equivalent is a switchboard whose design has been verified to IEC 61439-1 and IEC 61439-2 (both 2020 editions), with routine verification of each panel built. Ask for those reports rather than a type-test certificate.
Is IEC 60439 still valid for switchgear?
No. IEC lists IEC 60439-1:1999 as replaced by IEC 61439-1:2009, and the current edition is IEC 61439-1:2020. Specifications that still cite IEC 60439 should be updated, and bidders offering assemblies should provide IEC 61439 design verification evidence for the configuration offered.
What is a licensed or authorised panel builder?
It is a panel builder that a switchgear brand has approved to manufacture its switchboard system, such as Siemens' certified SIVACON technology partners. The builder relies on the brand's design verification and carries out routine verification of each panel. Ask for the brand's current letter naming the builder and system.
What is the difference between design verification and routine verification?
Design verification, in clause 10 of IEC 61439-1, proves that a switchboard design meets the standard, covering items such as temperature rise, short-circuit withstand and dielectric properties. Routine verification, in clause 11, is carried out on every panel built and checks items such as protection, wiring, mechanical operation, dielectric properties and function.
Is a panel with branded breakers automatically design verified?
The breaker maker's certificates cover only the breakers, not the assembly. If the builder designed its own enclosure and busbar system, ask for the design verification evidence for that assembly design, covering temperature rise and short-circuit withstand at your ratings. Without it, the panel has not been shown to meet IEC 61439 as a whole.
How do I choose between switchgear companies in the UAE?
Compare them on evidence: IEC 61439 design verification for the ratings you need, routine test certificates, partner status where claimed, test facilities, approved list status with your consultant or utility, and component conformity certificates. Then compare price and delivery on bids made to the same specification.
How VRF and chilled water systems differ, where VRF runs out of capacity, refrigerant safety in small rooms, part-load and high ambient ratings, district cooling as a third option, and an RFQ checklist.
Where LV ends and MV begins, how GIS and AIS differ in size, cost and maintenance, what SF6 rules mean for Gulf buyers, how ring main units work and how to read an MV datasheet.
Wall split, ducted split, package or window unit: how they differ, what Saudi and UAE efficiency rules require of each, how they cope at 46°C, and which suits villas, offices and warehouses.